Bridge Timeline


Our model Popsicles Bridge is a 7-week project with detailed tasks respect to specific time periods. The table 2 illustrates our project timeline for a 7-week duration:


            Tasks                Week

1
2
3
4
5
6
7
1.Design
x
x





2.Building


x
x
x


3.Verification




x
x









Table 2: Project Timeline.
     1.     Design
  • Begin to research about topics related to bridge structure and construction.
  • General rough sketch of Pratt Truss structure and dimensions
  • Generate detailed sketch on Visual Analysis.
  • Use Visual Analysis tools to test the geometry and compare the distribution of forces between positions
  • Estimate the weight the bridge can load

     2.     Physical building the design.
  • Come up with a blueprint of the two sides, middle part and beams with detailed layers of Popsicle sticks
  • Left side is built in week 3, right side in week 4, middle part and general fabricated in week 5
 3. Verification
  • We will test it with 50lbs first and increase up to 100lbs mass
  • Try to test if the load is placed in the middle and from the sides
  • May come up with solution to increase the load